Sanctuary Mount Pleasant is NOW 95% SOLD with construction now halfway and is estimated to be completed early 2022!

Despite WA going into a 4 day full lockdown again recently and the rainy weather as of late, the construction process is still progressing impressively at Sanctuary.

Details of works completed last month are as follows:

  • Installation of remaining boundary AFS wall systems
  • Pouring of level 4 suspended slab back half and front half
  • Pouring of all level 4 columns and AFS
  • Pouring of level 5 suspended slab back half and front half
  • Level 2 wall framing
  • Continue first fix services to level 1 and level 2
  • Start first fix to level 2
  • Start wall framing to level 2

 

95% of the apartments have been sold at Sanctuary Mount Pleasant.