How amazing it is to see this building develop over this time.
- Internal wall framing nearing completion on level 7.
- Internal wall linings in progress up to level 6.
- Mechanical installation in progress up to levels 5 & 6.
- External Hebel wall cladding in progress on levels 6 & 7.
- Window installation in progress on levels 6 & 7.
- Bathroom wall tiling in progress up to level 3.
- Bathroom vanity cabinets installation in progress on level 2.
- External rendering in progress up to level 4.